Project description

Microsoft Corporation India, one of the fastest growing subsidiaries of Microsoft Corporation, constructed this 12,000 square metre sales and marketing headquarters in Gurgaon. Partition walls and false ceilings for the entire office space were executed with Gyproc plasterboard and metal systems, and partition walls with Fireline plasterboard were used to achieve the fire performance requirements. For the wet area partition wall we opted for the Gyproc Moisture Resistant board with tile fixings on it. The architect and client were very particular about each and every minute detail. It was demanding from this perspective for the contractor to achieve such a quality finish with high attention to detail within the stipulated time frame of 90 days. PMC for the project received an award from Microsoft Corporation for the exemplary finish of the project. Furthermore, use of the MR plasterboard in wet area partition walls has always been a challenge in India, and this project successfully executed the wet area system.

Contractor

Ambience Interiors Pvt Ltd

Ambience Interiors is an interior fit out company with over two decades of experience in the Industry. They specialize in GC format & execute projects all over India providing end-to-end solutions including Civil, Interior, Electrical, Low Voltage, HVAC, AV and Networking. We have minimum dependency on external resources and have strong in-house capabilities, which results in a seamless experience for the client.

Key Achievements

  • PMC for the project received award from Microsoft Corporation for the finishing project in exemplary finish taking care of tiny detailing. Wet area partition execution has given boost to architect to offer MR board partition for all future projects.

Key Challenges

  • The architect and client were very particular about each and every minute detail. It was demanding for the contractor to achieve such performance with such high attention to detail within the stipulated time frame of 90 days.
  • Usage of Moisture resistant plasterboard and tile fixing on it in the wet area partition initially was met with a lack of confidence from the architect’s side initially.

Stakeholders

Building owner:
Microsoft Corporation
Architect:
DSP Architects, Gurgaon
Main contractor:
Ambience Interiors Pvt Ltd
Photographer:
Kapil Kumar
Saint-Gobain Team:
Sachin Gupta